设为首页收藏本站

最大的系统仿真与系统优化公益交流社区

 找回密码
 注册

QQ登录

只需一步,快速开始

查看: 1890|回复: 1

Availablity and OEE

[复制链接]
发表于 2008-9-2 12:06:43 | 显示全部楼层 |阅读模式
If a machine goes down for maintenance issues on 2nd shift and doesn't run again for 3 shifts, how is that calculated for OEE. Is availability 0% for those shifts?
 楼主| 发表于 2008-9-2 12:06:57 | 显示全部楼层
That depends on wether the machine was scheduled to run for those three shifts.

If the machine went down with 30 minutes left in the second shift it might have taken 30 minutes to fix. If the machine wasn't scheduled to run for the next three shifts and started up the next time it was needed, than availability should be calculated with only a 30 minute loss.

If, on the other hand, the machine went down with 30 minutes left in the second shift and it took 3 shifts + 30 minutes to get fixed, than the availability should be calculated with a 3 shift + 30 minute loss.

Availability is a measure of just what it says. What percentage of the time is the machine available to run when we want it to run?
您需要登录后才可以回帖 登录 | 注册

本版积分规则

QQ|Archiver|手机版|SimulWay 道于仿真   

GMT+8, 2024-11-25 17:13 , Processed in 0.016854 second(s), 14 queries .

Powered by Discuz! X3.4 Licensed

© 2001-2017 Comsenz Inc.

快速回复 返回顶部 返回列表